Raise boiler
steam pressure. Near set pressure, lift the stem manually by using rope on the
hand pop level. Increase pressure and confirm that the valve is opening at the
required set value. Start from the highest set pressure valve. Jack close the
low set pressure valves.
Confirm blow
down. It shall be between 2 to 5%.
Lift : The amount
of raise
of stem while lifting is called “lift”.
Blow down : The difference between set pressure & reseat pressure
Expressed in Æ
percentage of set pressure.
Adjustment :
Lower ring adj :- To set a clear
popping, to close slowly. (To avoid
Simmering & chattering ).
To reduce simmer, move the lower ring upward
ie. Anticlockwise direction.
1 notch =
42.2ksc.
Upper ring adj. :- To adjust blow down .
To reduce
blow down, move the upper ring upward,
ie.,
turn anticlockwise.
To
increase blow down , move the ring
downward