A process undertaken during initial plant installation, to remove any mill
scale in SH tubes and pipes by blowing steam and venting out the same is known
as steam blowing. Continuous and Puff Steam blow methods are used. In
continuous method the boiler shall be prepared for full load and the steam at
full load flow, pressure and temperature shall be blown for some hours. In
Puffing method, pressure in the boiler will be raised to 250 Deg.C, at around
40 bar, and the stop valve in the temporary pipe is opened quickly. This will
create a sudden change in velocity in the pipe. It is claimed that this the
best economical method. A target steel plate is put at the end of the pipeline
sections and the same is observed for the indentations after the steam blow to
establish the cleanliness of the steam pipes. Since the steam admitted to
turbine should not contain any contaminant (damages the turbine internals), the
Turbine commissioning in-charge will give clearance for the completion of
satisfactory steam blowing operation.