30.What is the procedure for pre-commissioning a soot blower after completion of erection?

Soot blower shall have a minimum slope of 5 deg. Towards the furnace, to clear the condensate after operation. The furnace will have expansion of furnace when it is on load. The other end will be supported from structure with slot for sliding.


The cold condition shall have slope to provide the above slop during hot condition.